Waterways Commission |
|
|
|
|
Capital Outlay Plan
FY11-FY17 |
|
|
|
|
FY11 |
FY12 |
FY13 |
FY14 |
FY 15 |
FY 16 |
FY 17 |
FY 17 |
FY 18 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Harbor Planning Article |
|
|
|
|
1. Saquatucket Harbor |
|
|
|
|
|
a. North bulkhead (plus west ramp) 584' |
|
|
|
|
|
|
|
i. Maintenance |
|
|
|
$200,000 |
|
|
|
|
ii. Replacement |
|
|
|
|
$1,500,000 |
|
|
|
b. East bulkhead (old fuel
dock & east side ramp) 242' |
|
|
|
|
|
|
|
iii. Replacement |
|
|
|
|
|
$700,200 |
|
|
|
iv. Pilings |
|
|
|
|
|
3. Steel remaining 24 |
|
|
|
|
|
1. Floats |
|
|
|
|
$275,000 |
|
|
|
vii. Downey property
(adjacent to marina) |
|
$1,250,000 |
|
|
|
|
|
1. Rack storage for smaller
boats |
|
|
|
|
|
2. Increase parking |
|
$200,000 |
|
|
|
|
|
xii. Bank street
harbormaster workshop |
|
|
|
|
2. Move workshop to Downey
property |
|
|
|
|
Channel to tip of jetties |
|
|
|
|
Dredging inner Channel &
marina |
|
|
|
|
$2,000,000 |
|
|
viii. Outer channel |
|
|
|
|
|
1. Dredging (7,000 cu yds beach sand long haul) |
$77,000 |
|
|
|
$90,000 |
|
|
|
|
2. Allen Harbor |
|
|
|
|
|
a. Inner basin |
|
|
|
|
|
i. Bulkhead-new south facing
blkhd |
|
$260,000 |
|
|
|
|
ii. Pilings/docks |
|
|
|
|
|
v. Dredging |
|
$92,000 |
|
|
|
|
|
vi. Parking Lot |
|
|
$100,000 |
|
|
|
|
|
b. Jetty Area-from tip to
where rock ends |
|
|
|
$1,200,000 |
|
|
c. Outer channel |
|
|
|
|
|
i. Dredging (8,000
cu.yds beach sand long haul) |
$88,000 |
|
$60,000 |
|
$90,000 |
|
$70,000 |
|
$70,000 |
|
|
d. Inner basin to jetty
(inner end) |
|
|
|
|
|
i. Dredging (40,000 cu yds of sludge) |
|
$2,500,000 |
|
|
|
|
|
3. Wychmere Inner Harbor |
|
|
|
|
|
a. Channel from Outer to
Inner Harbors |
|
|
|
|
|
|
|
i. Dredge |
|
|
$40,000 |
|
|
$40,000 |
|
|
|
|
b. Basin |
|
|
|
|
|
i. Dredge |
|
|
|
|
$2,500,000 |
|
|
|
Town Dock |
|
|
|
|
|
ii. Paving, storm treat
removal & basin installation |
|
$167,307 |
|
|
|
|
|
iii. East side |
|
|
|
|
|
1. Extend bulkhead towards
restrooms????????? |
|
|
|
|
|
|
|
2. Replace Restrooms |
|
$50,000 |
|
|
|
|
|
4. Wychmere Outer Harbor |
|
|
|
|
|
1. Needs raising to be a
“Harbor of Refuge” |
|
|
|
|
|
|
|
2. Entrance Light-West Jetty |
|
|
|
|
|
1. Lengthen |
|
|
|
|
|
|
v. Basin |
|
|
|
|
|
1. Dredge |
|
|
|
160000 |
|
|
|
|
a. More moorings possible |
|
|
|
|
|
|
2. Deepen |
|
|
|
|
|
|
5. Round Cove |
|
|
|
|
|
a. Opening from Pleasant Bay |
|
|
|
|
|
i. Dredging |
$35,000 |
|
$35,000 |
|
$35,000 |
|
|
|
b. Basin |
|
|
|
|
|
i. Dredging |
|
|
|
|
|
|
|
i. Non-buildable lot |
|
|
|
|
|
ii. Expanded parking |
|
|
|
|
|
|
|
f. Ramp |
|
|
|
|
|
|
|
|
h. Bulkhead |
|
|
|
$300,000 |
|
|
|
|
6. Herring River |
|
|
|
|
|
i. Dredging |
|
$50,000 |
|
|
|
|
|
Replace Wixon Dock |
|
$45,000 |
|
|
|
|
|
ii. Pave ramp |
|
|
|
|
|
|
7. Town Ramp-Rt 28 |
|
|
|
|
|
Paved Ramp |
|
$100,000 |
|
|
|
|
TOTAL BY YEAR |
$200,000 |
$4,012,307 |
$542,000 |
$295,000 |
$680,000 |
$475,000 |
$4,105,000 |
$700,200 |
$3,270,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
SHORT ITEMS |
|
|
|
|
|
|
|
|
|
|
|
FY11 |
FY12 |
FY13 |
FY14 |
FY 15 |
FY 16 |
|
|
Saquatucket Harbor |
|
|
|
|
|
|
|
|
Washdown system |
|
$35,000 |
|
|
|
East Bulkhead (old fuel dock)
maintenance |
|
|
|
|
Electric/water towers |
|
|
$50,000 |
|
|
Allen Harbor |
|
|
|
|
Rest Rooms |
|
$50,000 |
|
|
|
Replacement of jettty light |
|
$15,000 |
|
|
|
|
Wychmere |
|
|
$15,000 |
|
|
Replace Dingy Dock |
|
|
|
|
Fuel Dock fill and expand
parking |
|
|
|
|
Needs raising outer Harbor
beakwater |
|
|
|
|
|
Round Cove |
|
|
|
Replace dock/float |
|
$35,000 |
|
|
TOTAL BY YEAR |
$0 |
$0 |
$15,000 |
$50,000 |
$35,000 |
$65,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|